Formula to display next Friday from B1 works except on the Friday itself.

S

StargateFan

I found a formula for displaying the next Friday from the user input
date in B1. It works great except if the input date is a Friday. I
need a spreadsheet that shows invoicing dates, which occur every
Friday. But if the start date happens to be a Friday, need to have
the list include that Friday.

=B1-WEEKDAY(B1-4,2)+8

If I input this week's Friday in B1 (August 12, 2011), the list starts
on August 19th in B2 when it should actually say August 12th. For all
other days of the week it seems to work fine.

Thanks in advance for any help.

Cheers! :eek:D
 
C

Claus Busch

Hi,

Am Wed, 10 Aug 2011 05:40:38 -0700 (PDT) schrieb StargateFan:
=B1-WEEKDAY(B1-4,2)+8

If I input this week's Friday in B1 (August 12, 2011), the list starts
on August 19th in B2 when it should actually say August 12th. For all
other days of the week it seems to work fine.

try:
=B1+(MOD(B1-2,7)+1>5)*7+4-MOD(B1-2,7)


Regards
Claus Busch
 
D

Don Guillett

Hi,

Am Wed, 10 Aug 2011 05:40:38 -0700 (PDT) schrieb StargateFan:



try:
=B1+(MOD(B1-2,7)+1>5)*7+4-MOD(B1-2,7)

Regards
Claus Busch

Or
=B1-WEEKDAY(B1,3)+IF(WEEKDAY(B1,3)>4,11,4)
 
C

Claus Busch

Am Wed, 10 Aug 2011 06:36:10 -0700 (PDT) schrieb Don Guillett:
=B1-WEEKDAY(B1,3)+IF(WEEKDAY(B1,3)>4,11,4)

or
=B1+(WEEKDAY(B1,2)>5)*7+(5-WEEKDAY(B1,2))


Regards
Claus Busch
 
S

StargateFan

I found a formula for displaying the next Friday from the user input
date in B1. It works great except if the input date is a Friday. I
need a spreadsheet that shows invoicing dates, which occur every
Friday. But if the start date happens to be a Friday, need to have
the list include that Friday.

=B1-WEEKDAY(B1-4,2)+8

If I input this week's Friday in B1 (August 12, 2011), the list starts
on August 19th in B2 when it should actually say August 12th. For all
other days of the week it seems to work fine.

Thanks in advance for any help.

Cheers! :eek:D

Thanks much for everyone's replies. They all seemed to work just
great so I just picked one to put into my spreadsheet. The new
printout covers next few months and gives me one less thing to have to
stop and do manually. Cheers.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top