G
Gabi
Dear all,
I like to do the following:
show resource ID's of sub-level tasks also in the summary task so that I am
able to show these in the graphical area on summary level.
I tried to use a custom field which contains e.g. the information of the
standard field "resource ID" but this is only possible in a text field -
unfortunately, I did not find a way to customize the field to roll this
information up.
Any idea for a formula to do so?
Thanks much in advance,
best regards
Gabi
I like to do the following:
show resource ID's of sub-level tasks also in the summary task so that I am
able to show these in the graphical area on summary level.
I tried to use a custom field which contains e.g. the information of the
standard field "resource ID" but this is only possible in a text field -
unfortunately, I did not find a way to customize the field to roll this
information up.
Any idea for a formula to do so?
Thanks much in advance,
best regards
Gabi