Dear all,
I like to do the following:
show resource ID's of sub-level tasks also in the summary task so that I am
able to show these in the graphical area on summary level.
I tried to use a custom field which contains e.g. the information of the
standard field "resource ID" but this is only possible in a text field -
unfortunately, I did not find a way to customize the field to roll this
information up.
Any idea for a formula to do so?
Thanks much in advance,
best regards
Gabi
 
G

Gérard Ducouret

Hello Gabi,
A formula cannot do that because all the addresses of a formula are
"horizontal" : on the same row. Only a VBA procedure could do that.

Gérard Ducouret
 
M

Mike Glen

Hi Gabis,

Also, not only can't you choose a field for Resource ID in a Gantt chart,
but you should be aware that the Resource ID may not be constant. Inserting
or deleting a resource in the Resource Sheet view will renumber the IDs.
You can also sort the data and permanently renumber them.

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 
G

Gabi

Hi Mike,
sorry, I mistyped... I wanted to use the "resource initials" information.
BR
Gabi
 
M

Mike Glen

OK, Gabus. Project will not roll-up resource initials as it is possible to
assign resources themselves to summary tasks and these would conflict.

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 
G

Gabi

Hi Gérard,
thanks for the hint.
Did anyone out there have already the same need so that a VBA for this might
exist already?
BR
Gabi
 
G

Gabi

Hi Mike,

thanks for the comment, that's right!
How about if I use the resource initials for internal resources, a text
field for the initials of external resources and create a new text field
where I can combine the content of these 2 by a formula. Would it be possible
to roll-up this text field into the summary?

Thanks and kind regards
Gabi
 
M

Mike Glen

You're welcome, Gabi :) But the answer is still no. The best I can offer
is for you to type in the initials into a Text field which you can then show
on the summary line - you'll have to do it for every summary.

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 
G

Gabi

:-(((
but thanks anyway!

Mike Glen said:
You're welcome, Gabi :) But the answer is still no. The best I can offer
is for you to type in the initials into a Text field which you can then show
on the summary line - you'll have to do it for every summary.

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 
J

Jack Rnl

As I want to reorder my resources permanently based on the work they have done before exporting them to Excel (I create a sheet for each resource, so they will be in order of the amount of work), I would like to know HOW you can change the Resource-IDs .

In the 'View | Resource Sheet' I sorted on 'Work' and also see the 'ID' column. But I can't change the 'ID' values, nor do I see an option to permanently renumber the resources.
I'm using MS Project 2003




Mike Glen wrote:

Re: formula to show text information from sub-level task in summary ta
02-Sep-08

Hi Gabis

Also, not only can't you choose a field for Resource ID in a Gantt chart,
but you should be aware that the Resource ID may not be constant. Inserting
or deleting a resource in the Resource Sheet view will renumber the IDs.
You can also sort the data and permanently renumber them

Mike Gle
Project MV
See http://tinyurl.com/2xbhc for my free Project Tutorial


G?rard Ducouret wrote:

EggHeadCafe - Software Developer Portal of Choice
WPF - XAML TabControl SelectionChanged Threading Errors
http://www.eggheadcafe.com/tutorial...42-f22d79d6f8c5/wpf--xaml-tabcontrol-sel.aspx
 
R

Rob Schneider

You can't change the ID column, AFAIK and understand. In fact, Project
uses the ID internally as the "identifier" of the resourc. If you could
change it, it breaks everything. Why not just force the order you want,
both in Project simply clicking on the Work Columm and pick "sort by"?
This can be automated (although I don't know if the order "sticks" in
the export file). Experiment. But changing ID field to force a sort
order isn't the right approach, IMHO.

--rms

www.rmschneider.com
 
R

Rob Schneider

Trevor,
Cool. I never ever looked closely at the dialogue box for sorting. That
is a demo of waht is so interesting about Project as there is always
more to learn about it. Thanks.

--rms

www.rmschneider.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top