S
scot.milroy
Hello again,
My client wish to remove the subjectivity of the percent complete
field. I have set up an Enterprise Outline Code that is a drop-down
with the 0, 50 and 100 percent complete. I have set it up on the
timesheet at the assignement level so that the resource can choose 0,
50 or 100% complete. I would like to create a formula that once the
update is accepted by the PM the real % complete is updated according
to what the resource chose in the Enterprise Outline Code Number 1
drop-down.
Any ideas on this? I have tried several formulas but am wondering if
this is a macro function that would need to be written.
Any direction would be greatly appreciated.
Thanks,
Scot
My client wish to remove the subjectivity of the percent complete
field. I have set up an Enterprise Outline Code that is a drop-down
with the 0, 50 and 100 percent complete. I have set it up on the
timesheet at the assignement level so that the resource can choose 0,
50 or 100% complete. I would like to create a formula that once the
update is accepted by the PM the real % complete is updated according
to what the resource chose in the Enterprise Outline Code Number 1
drop-down.
Any ideas on this? I have tried several formulas but am wondering if
this is a macro function that would need to be written.
Any direction would be greatly appreciated.
Thanks,
Scot