J
JABAR
We use MS Professional and Project Server 2007.
First problem
Formula which are define in Professional disappear or destroy when we move
from Professional to Server and back. It’s look like Project Server don’t
understand formula Professional and change or delete it.
Example
We define column ‘cost’ in Professional CCur(IIf([Praca wg
pbaz.]<>0;IIf([Group of resource]='K';400*[Baseline work time]/480;0);0)) lub
IIf([baseline work]<>0;IIf([Group of resource]='K';400*[Baseline work
time]/480;0);0). The Project Professional works well, but Project Server
(after publish) delete this formula, which we see when we take project back
to Professional.
Second problem
The formula in Professional for ex ‘130,25’ it’s change to ‘130;25’ when we
move to Project Server and back project from Server to professional.
Thanks for any help
Jacek & Agnieszka
First problem
Formula which are define in Professional disappear or destroy when we move
from Professional to Server and back. It’s look like Project Server don’t
understand formula Professional and change or delete it.
Example
We define column ‘cost’ in Professional CCur(IIf([Praca wg
pbaz.]<>0;IIf([Group of resource]='K';400*[Baseline work time]/480;0);0)) lub
IIf([baseline work]<>0;IIf([Group of resource]='K';400*[Baseline work
time]/480;0);0). The Project Professional works well, but Project Server
(after publish) delete this formula, which we see when we take project back
to Professional.
Second problem
The formula in Professional for ex ‘130,25’ it’s change to ‘130;25’ when we
move to Project Server and back project from Server to professional.
Thanks for any help
Jacek & Agnieszka