J
jp
Hi,
I'm trying to figure out how to do the following:
Add a custom field to the "Gantt Chart" called "Task_Status".
This "Task_Status" would have a pull down menu of 4 items:
1) Complete
2) Not Complete
3) In Progress
4) Up-coming task
So, if the value is "Complete" from the field called "Task_Status" then the
Task Name column is highlighted in green color. If the task is "Not Complete"
give the "Task Name" column a red color. If it is "In Progress" give it a
yello color
and finally if the task is "Up-coming" do nothing.
Thanks.
-JP
I'm trying to figure out how to do the following:
Add a custom field to the "Gantt Chart" called "Task_Status".
This "Task_Status" would have a pull down menu of 4 items:
1) Complete
2) Not Complete
3) In Progress
4) Up-coming task
So, if the value is "Complete" from the field called "Task_Status" then the
Task Name column is highlighted in green color. If the task is "Not Complete"
give the "Task Name" column a red color. If it is "In Progress" give it a
yello color
and finally if the task is "Up-coming" do nothing.
Thanks.
-JP