R
Riko Wichmann
Dear all,
is it possible to use a formular to calculate the standard cost rate for
a work resource?
We plan with a standard rate of x Euro in the year 2008, this rate is
supposed to increase by 1.5% per year due to inflation (both X and 1.5%
are "political" values).
Of course, I could define define per resource the proper dates with the
corresponding rate, but with many resources in the projects this is
slave work. Much mor convenient and less error prone would be the
possibility to enter someting like
rate = (1.015)^year-2008 * x
Is that at all possible?
I fear not, but maybe a macro can fill those fields properly ....
Thanks,
Riko
MS Project 2007 Enterprise
is it possible to use a formular to calculate the standard cost rate for
a work resource?
We plan with a standard rate of x Euro in the year 2008, this rate is
supposed to increase by 1.5% per year due to inflation (both X and 1.5%
are "political" values).
Of course, I could define define per resource the proper dates with the
corresponding rate, but with many resources in the projects this is
slave work. Much mor convenient and less error prone would be the
possibility to enter someting like
rate = (1.015)^year-2008 * x
Is that at all possible?
I fear not, but maybe a macro can fill those fields properly ....
Thanks,
Riko
MS Project 2007 Enterprise