E
Erkki
Hi.
I have customized a date field with the following formula : IIF
([Name]="Some task name";[Start];"NA")
Calculation for task and group summary rows is set to : Rollup - Maximum.
This produces an ERROR in the custom date field. Any ideas ?
PS Where are the formulas documented - syntax, examples...?
Thank You,
Erkki
I have customized a date field with the following formula : IIF
([Name]="Some task name";[Start];"NA")
Calculation for task and group summary rows is set to : Rollup - Maximum.
This produces an ERROR in the custom date field. Any ideas ?
PS Where are the formulas documented - syntax, examples...?
Thank You,
Erkki