D
DJ Huff
I have yet to be able to figure out the formulas that derive both Actual
Duration and BCWP when using actual data in my plans. I understand from
where the data is to come, but I have not found a consistent set of formulas
I can use to calculate Actual Duration, which is essential to calculating %
Complete...nor can I figure out how MSP (standalone 2007) calculates BCWP. I
have asked the question on this forum in the past as to how MSP calculates
the EV elements but have not gotten an answer I can use to run calculations
myself and have them = Actual Duration or BCWP I see in the plans.
Documentation says Actual Duration / Duration = % Complete (which is what I
have set for EV). I cannot figure out Actual Duration. It appears it may
use the baseline hours per day within a given period in some fashion, but my
calculation results have been inconsistent. I understood BCWP = % Complete *
BAC, but that has also been inconsistent. Some documentation implies BCWP
uses % Work Complete while others imply % Complete. I need to understand
this to be able to make the proper plan adjustments to keep the plans on
track.
Duration and BCWP when using actual data in my plans. I understand from
where the data is to come, but I have not found a consistent set of formulas
I can use to calculate Actual Duration, which is essential to calculating %
Complete...nor can I figure out how MSP (standalone 2007) calculates BCWP. I
have asked the question on this forum in the past as to how MSP calculates
the EV elements but have not gotten an answer I can use to run calculations
myself and have them = Actual Duration or BCWP I see in the plans.
Documentation says Actual Duration / Duration = % Complete (which is what I
have set for EV). I cannot figure out Actual Duration. It appears it may
use the baseline hours per day within a given period in some fashion, but my
calculation results have been inconsistent. I understood BCWP = % Complete *
BAC, but that has also been inconsistent. Some documentation implies BCWP
uses % Work Complete while others imply % Complete. I need to understand
this to be able to make the proper plan adjustments to keep the plans on
track.