I'm trying to create a Project Center view with stoplight indicators. The
formula I tested worked just fine with a task custom field, but failed to
work with an enteprise project field.
I modified the field in the enteprise global, saved the file and restarted
Project. Then I opened a project and looked in the project information dialog
box. The new field was there but the value was #ERROR.
Is there something special to do with formulas in enteprise project fields?
Thanks.
Jan M.
I'm trying to create a Project Center view with stoplight indicators. The
formula I tested worked just fine with a task custom field, but failed to
work with an enteprise project field.
I modified the field in the enteprise global, saved the file and restarted
Project. Then I opened a project and looked in the project information dialog
box. The new field was there but the value was #ERROR.
Is there something special to do with formulas in enteprise project fields?
Thanks.