Renate
Hi, new here, I've been reviewing the questions and answers regarding
formula...my question, and sorry if it's already been posted before, does
someone have a formula I can use (I'm not an IT person) to show the variance
between actual and baseline, including summary tasks. I need to show how far
behind the original schedule people are falling behind (sorry but I'm only
doing durations, no resource costs are included - that's on another program
and a whole other story) so I don't think the SPI etc. would work for me. I
have made a new view and am using the duration 1 column renamed to slipping
with the graphical indicators or RAG, but, alas, my formula's don't seem to
work, or maybe I need some additional columns? ( I made my view using the
projectexperts paper that was talked about in older posts) I know it's a
pretty basic schedule format, but I'm working on having the powers that be
upgrade to the server and then I can start rocking and show them what project
and really do! Thanks in advance
formula...my question, and sorry if it's already been posted before, does
someone have a formula I can use (I'm not an IT person) to show the variance
between actual and baseline, including summary tasks. I need to show how far
behind the original schedule people are falling behind (sorry but I'm only
doing durations, no resource costs are included - that's on another program
and a whole other story) so I don't think the SPI etc. would work for me. I
have made a new view and am using the duration 1 column renamed to slipping
with the graphical indicators or RAG, but, alas, my formula's don't seem to
work, or maybe I need some additional columns? ( I made my view using the
projectexperts paper that was talked about in older posts) I know it's a
pretty basic schedule format, but I'm working on having the powers that be
upgrade to the server and then I can start rocking and show them what project
and really do! Thanks in advance