Fractions in the summary task duration

P

PMad

I am confused as to why I am getting 1/3 and 2/3 fractions of days in a
couple of my summary task durations.....Thanks
 
S

salgud

I am confused as to why I am getting 1/3 and 2/3 fractions of days in a
couple of my summary task durations.....Thanks

Do you have sub-tasks with durations with fractions of days? I.e., 3hrs, or
12 hrs?
 
J

John

PMad said:
I am confused as to why I am getting 1/3 and 2/3 fractions of days in a
couple of my summary task durations.....Thanks

PMad,
Since summary line durations are defined by the difference in working
days between the start of the earliest task under the summary to the
finish of the latest task under the summary, a lead or lag between task
relationships can give partial day durations.

You might also want to check your calendar settings under
Tools/Options/Calendar tab (task duration is defined by the Hours per
day setting). Are the resources assigned to the tasks on the standard
calendar or do some have custom calendars? To get a quick assessment you
could use the Resource Usage view to look at how the resource work hours
are distributed.

Another helpful parameter is to set the date format to include the time
(i.e. Tools/Options/View tab). Look for task start and finish times that
fall mid-day.

Hope this helps.
John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top