A
Andreas Zoch
Hi,
I've some trouble with free slack information I get out of
my schedule. For instance I have two activities with an
FS+5d relationsship and a free slack of 10 days. If I
change the relationsship to FS the free slack changes to 5
days, which is correct. If I change it to FS-1d, the free
slacks is changed to 0 which seems to be wrong in my
opinion. Any advise to fix that?
Thanks, Andreas
I've some trouble with free slack information I get out of
my schedule. For instance I have two activities with an
FS+5d relationsship and a free slack of 10 days. If I
change the relationsship to FS the free slack changes to 5
days, which is correct. If I change it to FS-1d, the free
slacks is changed to 0 which seems to be wrong in my
opinion. Any advise to fix that?
Thanks, Andreas