I have a task (ASAP constraint) with FS relationship to three predecessors.
The latest finsh date of all three predecessors is 6 Sep 07. But the task
starts on 24 Sep 07.
If I change the constraint to ALAP and then back to ASAP, the task moves to
6 Sep 07, as expected.
Calculation is set to automatic; "Autolink Inserted or Moved Tasks" is set
to off; I'm using MS Project Standard 2003 11.0.2003.0816.15.
This is only one task, but I'm concerned this problem is recurring
throughout the rest of the project.
Can anyone help? Am I missing something simple?
The latest finsh date of all three predecessors is 6 Sep 07. But the task
starts on 24 Sep 07.
If I change the constraint to ALAP and then back to ASAP, the task moves to
6 Sep 07, as expected.
Calculation is set to automatic; "Autolink Inserted or Moved Tasks" is set
to off; I'm using MS Project Standard 2003 11.0.2003.0816.15.
This is only one task, but I'm concerned this problem is recurring
throughout the rest of the project.
Can anyone help? Am I missing something simple?