Is there a way that I can change the calendar for the calculation of FTE's in
Portfolio Server? It appears to calculate FTE's based on an 8 hour day,
resulting in my Project Server imported Resource Utilisation showing as 0.92
or something per FTE.
FYI, the export from PPS to PS Resource Plan the value is correct 1 FTE = 1
FTE, it's just when I Update Availability do I see these different values.
Any help would be great thanks,
Martin Laukkanen