J
Jan T.
Working overtime, there are two options. Get extra money
or have some extra days off later.
The table below shows Overtime worked in May.
Line Date Hrs
---------------------
1 05/01 3
2 05/02 1,5
3 05/05 2
4 05/06 4
5 05/07 1
6 05/08 2
7 05/10 8
What I want to do here, is take the overtime out
in free time, 2 days in august (Aug the 1. and 2.)
in stead of getting extra paid on my salary.
I will have a wizard that asks for a Start date where
I will write aug.1. Duration; 2 days. What I now
want is a function that groups together hours in
work days with 7.5 hrs a day (full time) by setting
vacation date in the last column.
As you can see under neeth, I have done this manually.
It is easy math when you do it manually.
However I want to have a function to do this automatically.
Line Date Hrs Used for vacation
-----------------------------------------
1 05/01 3 08/01
2 05/02 1,5 08/01
3 05/05 2 08/01
4 05/06 4 08/02
5 05/07 1 08/01
6 05/08 2 08/02
7 05/10 8 (need to split this first - se below)
8 a function takes care of this an adds:
9 05/10 1,5 08/02
10 05/10 6,5 overtime salary
The challenge is to pick the rows that makes up the sum 7.5 hrs
that is one work day, without having to split moore rows than
necessary. Then I put the date for vacation in the last column.
The function will have to continue until all rows needed do have
a date for vacation. The left overs, 6.5 hrs will be used another
time or it can be paid out as overtime. Got it?
One strategy could be to start with the lowest amount of hrs and write
the aug.1 then
add the second lowest number of hrs and so on until it reaches
7.5. But that is not always the best solution I quess. Say I
picked 4, 1.5 and 2. That would be exactly 7.5 hrs even I did not
pick all the smalest numbers (hrs).
How can I write an optimal function here?
Any suggestions for an optimal solution (function) to this challenge?
Thank you very much for helping.
Regards
Jan
or have some extra days off later.
The table below shows Overtime worked in May.
Line Date Hrs
---------------------
1 05/01 3
2 05/02 1,5
3 05/05 2
4 05/06 4
5 05/07 1
6 05/08 2
7 05/10 8
What I want to do here, is take the overtime out
in free time, 2 days in august (Aug the 1. and 2.)
in stead of getting extra paid on my salary.
I will have a wizard that asks for a Start date where
I will write aug.1. Duration; 2 days. What I now
want is a function that groups together hours in
work days with 7.5 hrs a day (full time) by setting
vacation date in the last column.
As you can see under neeth, I have done this manually.
It is easy math when you do it manually.
However I want to have a function to do this automatically.
Line Date Hrs Used for vacation
-----------------------------------------
1 05/01 3 08/01
2 05/02 1,5 08/01
3 05/05 2 08/01
4 05/06 4 08/02
5 05/07 1 08/01
6 05/08 2 08/02
7 05/10 8 (need to split this first - se below)
8 a function takes care of this an adds:
9 05/10 1,5 08/02
10 05/10 6,5 overtime salary
The challenge is to pick the rows that makes up the sum 7.5 hrs
that is one work day, without having to split moore rows than
necessary. Then I put the date for vacation in the last column.
The function will have to continue until all rows needed do have
a date for vacation. The left overs, 6.5 hrs will be used another
time or it can be paid out as overtime. Got it?
One strategy could be to start with the lowest amount of hrs and write
the aug.1 then
add the second lowest number of hrs and so on until it reaches
7.5. But that is not always the best solution I quess. Say I
picked 4, 1.5 and 2. That would be exactly 7.5 hrs even I did not
pick all the smalest numbers (hrs).
How can I write an optimal function here?
Any suggestions for an optimal solution (function) to this challenge?
Thank you very much for helping.
Regards
Jan