P
Paul Willemsen (Wortell)
Hi there, at my company we are working serveral years with Project for
Projectmanagement. At this moment I am implementing MS Projectserver 2007 (as
a 9times MS Gold Partner we have to ;-))
I want to divide the organisation in four roles:
- Project manager --> Creating new project, assigning global functions
(example Sharepoint.Net Developer
- Technical coordinator --> Assigning more detailed function (Example
Senior.Sharepoint.net Developer)
- Resourceplanner --> Assigning the person that is available at that time
- Teammember --> person that is planned
What is the best way of doing this?
- By RBS
- By Teamnames in combination with "generic" Teamname resource
Or is there another way of doing this?
And last question:
Is there a way of sync the "note" informatie of Projecttask in Outlook
calendar Item?
Regards
Paul Willemsen
Projectmanagement. At this moment I am implementing MS Projectserver 2007 (as
a 9times MS Gold Partner we have to ;-))
I want to divide the organisation in four roles:
- Project manager --> Creating new project, assigning global functions
(example Sharepoint.Net Developer
- Technical coordinator --> Assigning more detailed function (Example
Senior.Sharepoint.net Developer)
- Resourceplanner --> Assigning the person that is available at that time
- Teammember --> person that is planned
What is the best way of doing this?
- By RBS
- By Teamnames in combination with "generic" Teamname resource
Or is there another way of doing this?
And last question:
Is there a way of sync the "note" informatie of Projecttask in Outlook
calendar Item?
Regards
Paul Willemsen