A
AC
Hi all, got a fundamental query, need some
enlightenments...
Max Units can be found in the Resource sheet. Should I
preset at 20% or 80% or even 100%(for example). I am in
the opinion of setting at 20% cos I want only 20% of the
resource time being allocated every time he is being
assigned to a task.
By doing this, I will still have available time on that
resource to be allocated to another task. Is this
thinking correct. If not, how can I achieve this? Or what
is the correct concept?
Next question - Everyone is not efficient to work 8 hrs
per day. How can I cater of this inefficiency? Can I set
the Max Units to 80% or 90% then? The balance will be
allocated for nature call, short break during work...Or is
there another way to configure this setting?
Appreciate your attention.
AC
enlightenments...
Max Units can be found in the Resource sheet. Should I
preset at 20% or 80% or even 100%(for example). I am in
the opinion of setting at 20% cos I want only 20% of the
resource time being allocated every time he is being
assigned to a task.
By doing this, I will still have available time on that
resource to be allocated to another task. Is this
thinking correct. If not, how can I achieve this? Or what
is the correct concept?
Next question - Everyone is not efficient to work 8 hrs
per day. How can I cater of this inefficiency? Can I set
the Max Units to 80% or 90% then? The balance will be
allocated for nature call, short break during work...Or is
there another way to configure this setting?
Appreciate your attention.
AC