Future Resource Hours Being Added to Work Not Started

J

Jennifer

Is anyone seeing future hours being entered into Project 2007 plans for
tasks? Project managers review and accept resources’ tasks hours weekly. But
I’m seeing tasks with actual work hours, in them, sometime two months ahead
of the project. Our tasks are set to Fixed Duration. The hours that I’m
seeing are like .38 .08 . .03. We account hours to the .5 only. Please let me
know.
Thanks!!!
 
A

Andrew Lavinsky

Do you see the hours prior to acceptance, or after they've been imported into
your project plan?
 
G

Gary L. Chefetz

Jennifer:

As Larry states, this bug is supposed to be fixed in the Dec 2009 CU.
Inasmuch as the Feb 2010 CU is available, you might just as well go with
that one.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top