Urgent!No Risks & Issues Assigned on PWA
All,
I have a question regarding task types.
Initally I tried fixed work on enterprise template and folllowed on all
projects.
But this changes the duration and resource units %. But we want to set the
resource units to 10 % of entire duration. So we switched to fixed duration.
But now when we put the more actual hours and remaining hours on pwa
timesheet. After saving the project plan, it bumps up the resource units to
200%.
We don't want this, but we want the units to stay as 10% and the duration
should change and not work. Is this possible?.
Note: Timesheet tracking on actual hr entry day by day.
many thanks!
sankar
I have a question regarding task types.
Initally I tried fixed work on enterprise template and folllowed on all
projects.
But this changes the duration and resource units %. But we want to set the
resource units to 10 % of entire duration. So we switched to fixed duration.
But now when we put the more actual hours and remaining hours on pwa
timesheet. After saving the project plan, it bumps up the resource units to
200%.
We don't want this, but we want the units to stay as 10% and the duration
should change and not work. Is this possible?.
Note: Timesheet tracking on actual hr entry day by day.
many thanks!
sankar