Ganatt View, End Dates

C

Christine

Questions

(1) When I change to a Gnatt Chart view, certain summary tasks change form a non-italicized black font to a red italicized font. Other summary tasks turn blue. Why is this? Also, why doesn't a bar graph appear for the red summary tasks

(2) When I change the duration of a task, I’d like the start date to change, and the end date to remain the same. How can I do this

Thanks

Christin
 
G

Gérard Ducouret

Hello Christine,
Ganatt Gnatt views ? Poor Mister Henry L. Gantt ! ;-)

Question 1 : Obviously somebody customized the Gantt Chart: look at Format /
Bar Styles... to understand what is at the origin of these colors. Or also
Format / Bar... if it is a specific custom.

Question 2 : Try the As Late As Possible constraint type : Advanced tab of
the Task Information dialog.

Hope this helps,

Gérard Ducouret

Christine said:
Questions:

(1) When I change to a Gnatt Chart view, certain summary tasks change
form a non-italicized black font to a red italicized font. Other summary
tasks turn blue. Why is this? Also, why doesn't a bar graph appear for
the red summary tasks?
(2) When I change the duration of a task, I'd like the start date to
change, and the end date to remain the same. How can I do this?
 
M

Mike Glen

OK Christine,

1. Try Format/Test Styles.
2. You neet to set a Finish No Earlier Than constraint on the appropriate
tasks. Not a recommended technique as your project will lose flexibility
and limit what you can do to manage slippage, etc.


Mike Glen
Project MVP
 
J

Jan De Messemaeker

Hi Christine,

To change Font Colors:
- Format, Text Styles, hope you find a suitable category
- Or Format, Font for selected task fields

For your second question, give the task a constraint of must finish on.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
Christine said:
Thanks but this didn't work for me.

1. Format/Bar Styles and Format/Bar don't let me change the font/color of
the task name. (The seem to only control the appearance of the Gnatt bars).
2. I selected Project/Task Information and set the constraint to As Late
As Possible. This changed the finish date of the task to be the same as the
latest finish date in the project. That's not what I want. I'd like to be
able to change the duration of a task and have the start date (and not the
end date) move.
 