R
Rob
I found the below link in these discussion groups and I am trying to
incorporate this into My Project file for the very same reason as discussed
and the below link.
I cannot get this to work at all. I am using Project 2003 and I have
inserted a text column (Text 1) and I directly copy and pasted the below
formula from the below linked discussion. Nothing happened except that the
formula that I placed into the text field shows up but only as straight plain
text.
"w" & Format(DateAdd("d",7-Weekday([Finish]),[Finish]),"ww" & "'yy")
"w" & Format(DateAdd("d",7-Weekday([Finish]),[Finish]),"ww" & "'yy") & " "
& [Resource Names]
http://www.microsoft.com/office/com...ject&mid=9e5daeb2-93f4-438c-bcc5-9227508a17b1
I even tried my own with the below formula - (which is what I want to show);
&[Resource Names] & " - " & [% Complete]
Can someone please help me and explain what I am doing wrong?
Thanks Very Much In Advance,
Rob
incorporate this into My Project file for the very same reason as discussed
and the below link.
I cannot get this to work at all. I am using Project 2003 and I have
inserted a text column (Text 1) and I directly copy and pasted the below
formula from the below linked discussion. Nothing happened except that the
formula that I placed into the text field shows up but only as straight plain
text.
"w" & Format(DateAdd("d",7-Weekday([Finish]),[Finish]),"ww" & "'yy")
"w" & Format(DateAdd("d",7-Weekday([Finish]),[Finish]),"ww" & "'yy") & " "
& [Resource Names]
http://www.microsoft.com/office/com...ject&mid=9e5daeb2-93f4-438c-bcc5-9227508a17b1
I even tried my own with the below formula - (which is what I want to show);
&[Resource Names] & " - " & [% Complete]
Can someone please help me and explain what I am doing wrong?
Thanks Very Much In Advance,
Rob