Gannt Chart and Start Date

J

Joey

How can I change my view so that, in the Gannt view,
there isn't a blank week showing first. I've checked and
double checked my start and end dates and can't get rid
of it. What am I doing wrong?
 
M

Mike Glen

Hi Joey,

Welcome to this Microsoft Project newsgroup :)

On my setup of Project 2003, I set the Gantt Chart view as I want it by
scrolling the chart, and then save it and shut down. When I open it again,
it is as I left it.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top