Gannt Chart Format

S

Scott

I would like to create a task tracking view using Baseline3 instead of
Baseline0. Can this be done? I cannot find a way to modify the format.
 
M

Marc Soester

Hi Scott,

The PWA Gantt chart only looks at the Baseline. I assume that you have
created several new baselines and no3 is now your actual one, which you would
like to display- fair enough :) - but unfortunalty there is no way to tell
PWA to look at Baseline 3.
The way I get arround this is as follow:
I always make Baseline (Baseline 0) my actual Baseline. Should I need to
re-baseline my project, the first thing I do is copy Baseline to Baseline1. I
then re-baseline my Baseline to the currenct values. Should I need to
re-baseline a second time, I then use Baseline and copy it to Baseline 2, and
once again amend my Baseline to the new value. This will ensure that my
Baseline (Baseline 0) is always the current baseline and PWA will display the
currect tracking gantt chart baseline.

I hope this information helps.
 
S

Scott

Ok..thanks. We use many baselines and Baseline0 is reserved for a special
metric in our process. Maybe I need to re-visit this. I probably will just
created the required view out of Reporting Services.
 