Gannt chart on PWA changing duration from orginal plan

S

Sim

Hi, on my gannt chart the durations are getting chnaged to something which i
dont have displayed in Microsoft project. For example if i have 7 days in
Microsoft Project it is displayed as 6.56days on PWA.

Has anybody got any ideas as to what i am doing wrong?

Thanks
 
G

Gérard Ducouret

Hello Sim,
May be are you using a calendar which is not the "Standard" one with the
standard slot times 8:00-12:00 and 13:00 - 17:00. Probably less than 8 h/day
..
Obviously, this issue is not addressed by MS.
 
S

Sim

I dont quite follow you, i am using the standard calendar with the times you
mentioned in the global template. Do i need to change the working time
somewhere else too?

I thank you for the post you wrote prior to this and also any further
information you post.



Gérard Ducouret said:
Hello Sim,
May be are you using a calendar which is not the "Standard" one with the
standard slot times 8:00-12:00 and 13:00 - 17:00. Probably less than 8 h/day
..
Obviously, this issue is not addressed by MS.

--
Gérard Ducouret [Project MVP]

Sim said:
Hi, on my gannt chart the durations are getting chnaged to something which i
dont have displayed in Microsoft project. For example if i have 7 days in
Microsoft Project it is displayed as 6.56days on PWA.

Has anybody got any ideas as to what i am doing wrong?

Thanks
 
D

Dale Howard [MVP]

Sim --

Open your project and then click Tools - Options - Calendar. Is the Hours
per day value set to something less than 8 hours? If so, reset the value to
8 hours and click OK. The Hours per day value is used to calculate Duration
in Microsoft Project. Let us know if this helps.




Sim said:
I dont quite follow you, i am using the standard calendar with the times
you
mentioned in the global template. Do i need to change the working time
somewhere else too?

I thank you for the post you wrote prior to this and also any further
information you post.



Gérard Ducouret said:
Hello Sim,
May be are you using a calendar which is not the "Standard" one with the
standard slot times 8:00-12:00 and 13:00 - 17:00. Probably less than 8
h/day
..
Obviously, this issue is not addressed by MS.

--
Gérard Ducouret [Project MVP]

Sim said:
Hi, on my gannt chart the durations are getting chnaged to something
which i
dont have displayed in Microsoft project. For example if i have 7 days
in
Microsoft Project it is displayed as 6.56days on PWA.

Has anybody got any ideas as to what i am doing wrong?

Thanks
 
S

Sim

looks to have helped thanks alot!

Sim said:
I dont quite follow you, i am using the standard calendar with the times you
mentioned in the global template. Do i need to change the working time
somewhere else too?

I thank you for the post you wrote prior to this and also any further
information you post.



Gérard Ducouret said:
Hello Sim,
May be are you using a calendar which is not the "Standard" one with the
standard slot times 8:00-12:00 and 13:00 - 17:00. Probably less than 8 h/day
..
Obviously, this issue is not addressed by MS.

--
Gérard Ducouret [Project MVP]

Sim said:
Hi, on my gannt chart the durations are getting chnaged to something which i
dont have displayed in Microsoft project. For example if i have 7 days in
Microsoft Project it is displayed as 6.56days on PWA.

Has anybody got any ideas as to what i am doing wrong?

Thanks
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top