Gannt Chart Wizard replaces Deliverable Start/finish to milestone

T

TomDeegan

I am using a Master schedule as a Program roll up schedule for many projects.
I am using Deliverables in the project schedules to be shown in the master
program schedule. When I first enter the deliverable the tasks in the
program schedule shows the length (start and finish dates). After I run the
Gannt Chart Wizard on the program, the Gannt now shows just the deliverable
as a milestone. I do not want these deliverables to be changed into
milestone, I want the program schedule to show the duration of the
deliverable. I used the Gannt Chart Wizard because I wanted to add the
deliverable task name to the Gannt chart.
 
J

Jan De Messemaeker

Hi,

So the conclusion is what I teach in my courses... avoid the Gantt Chart
Wizard, it has weaknesses in its design; use bar Styles instead.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 