R
Rusty
I have usually 10 or more projects in Project Server at
one time. From the Projects page I can view the project
summary information on the left (name, start date, finish
date, % comp., etc.), and the right side shows the Gant
Chart. The progress bar on the Gant chart is not
representative of the actual % complete for some of the
projects. For example, the project data on the left side
shows 50% complete, yet the progress bar on the Gant chart
indicates far less completed work. Please help me
understand why this is happening. Thank you.
one time. From the Projects page I can view the project
summary information on the left (name, start date, finish
date, % comp., etc.), and the right side shows the Gant
Chart. The progress bar on the Gant chart is not
representative of the actual % complete for some of the
projects. For example, the project data on the left side
shows 50% complete, yet the progress bar on the Gant chart
indicates far less completed work. Please help me
understand why this is happening. Thank you.