Gant Chart view missleading

R

Rusty

I have usually 10 or more projects in Project Server at
one time. From the Projects page I can view the project
summary information on the left (name, start date, finish
date, % comp., etc.), and the right side shows the Gant
Chart. The progress bar on the Gant chart is not
representative of the actual % complete for some of the
projects. For example, the project data on the left side
shows 50% complete, yet the progress bar on the Gant chart
indicates far less completed work. Please help me
understand why this is happening. Thank you.
 
R

rusty

Kevin,

Unfortunately, Microsoft Project is not perfect either.
The left side information was the same as the Summary info
on the Gantt chart. However, there was a drastic visible
difference between the two. This project did fall behind
and even when the project was marked 90% complete,
updated, saved, and reloaded-the Gantt chart still only
showed maybe 20% complete. Just wish I knew why it was
occuring. Thanks for the input.
 