G
Guest
Say I have two tasks of equal duration (1-day each). One task starts on
Tuesday November 24th and appears about a 1/4" long on the Gantt Chart. The
other task starts on Wednesday Nobember 25th and because of the Thanksgiving
holiday and weekend it appears to be over 1" long, because it stretches
across the holiday and the weekend.
Is there a way to have the Gantt bar start as a bar on Wednesday and then
thin down to a blue line or something over the holiday and weekend and then
covert back to a bar again on Monday the 30th?
It's just that this huge 1" wide blue bar looks like a much larger task that
the smaller 1/4" blue bar even though they are of equal duration.
Tuesday November 24th and appears about a 1/4" long on the Gantt Chart. The
other task starts on Wednesday Nobember 25th and because of the Thanksgiving
holiday and weekend it appears to be over 1" long, because it stretches
across the holiday and the weekend.
Is there a way to have the Gantt bar start as a bar on Wednesday and then
thin down to a blue line or something over the holiday and weekend and then
covert back to a bar again on Monday the 30th?
It's just that this huge 1" wide blue bar looks like a much larger task that
the smaller 1/4" blue bar even though they are of equal duration.