gantt bar start

T

Toltec

When I enter a new task, the gantt bar seems to start at the end of the first
day. In other words, if the duration is just 1 day, there is no bar. How do
I have it start at the begining of the first day? My timeline is weeks/days.
 
J

JulieS

Hello Toltec,

What time does the task start? It is usual for project to schedule
tasks to begin at the start date and time of the project but it sounds
as though the start time of the project is off.

Switch to a date format that shows time through Tools > Options, View
tab. Then check the project start date through Project > Project
Information.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 