GANTT Chart data cut-off

D

Dkline

Is there a way that you can add a vertical line to the gantt chart that
shows the data cut-off? (a line that goes across all the horizontal bars)?
We used to call it a "time-now" bar that you could adjust for any given
date. I don't know if that feature still exists or not. It would be nice to
show if studies are moving beyond the cut-off date
 
J

JackD

Right click on the gantt chart. Select "Gridlines", set the format for the
"current date" for the current date or "status date" if you want to show
status date.

You can set both current date and status date by going to the "Project Menu"
and selecting "Project Information". Then set the dates to whatever you
like.
 