Gantt Chart Date Range Question

M

Matt

I am wanting to display in greater detail, a section of
the gantt chart i.e. 2 months of my 1 year plan. The
surrounding date ranges can continue to be displayed with
less detail, but I would like to pinpoint the detail of
just that 2 month section. Can this be done? Any help
would be appreciated. Thanks
 
J

JulieD

Hi Matt

you can change the timescale units under Format / Timescale
you can print specific parts of your gantt chart using file / print and
setting a date range

Hope this helps
Cheers
JulieD
 