Gantt Chart Formatting In Project Professional

J

Jim

Is there a way to roll-out Gantt chart formatting so that it is applied to
all enterprise projects when opened in Project Professional? I've tried
making such changes in the Enterprise Global Template, but the changes are
not applied to the individual projects.
 
D

Dale Howard [MVP]

Jim --

Open the Enterprise Global file and then edit the Enterprise Gantt Chart and
Enterprise Entry table as you wish. You should NOT modify the regular Gantt
Chart view or Entry table, as this will cause an error message every time
your PM's open their projects. You will need to teach your PM's to apply
the Enterprise Gantt Chart view in their projects so that they can see the
standard look of the Gantt Chart. Hope this helps.
 