Gantt Chart Link Lines

T

TR

I'm finding that in some of my sub-activities within my linked project when moving some durations I'm losing link lines on the Gantt Chart, any suggestions
Thanks.
 
G

Gérard Ducouret

Hello TR,

May be the graphic card of your PC is a little bit weak. Refresh the screen
display by reducing then maximizing the Project window.
Hope this helps,

Gérard Ducouret [Project MVP]
PragmaSoft ® - Paris

TR said:
I'm finding that in some of my sub-activities within my linked project
when moving some durations I'm losing link lines on the Gantt Chart, any
suggestions?
 
M

Mike Glen

Hi TR,

Welcome to this Microsoft Project newsgroup :)

I'm not sure how you are "moving durations". Are you clicking and tragging
bars on the Gantt Chart? Not a good practice as if you do as this will
create constraints that will reduce the flexibility of your project. Start
date should be defined by the logical link from its predecessor, and finish
is calculated by Project from the Duration you type in.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top