Gantt chart not showing Deadline

J

Jane

using PS 2007 SP1

I have adjusted my Gantt Chart Formats including displaying Deadline. All
changes are reflected in the correct views except for Deadline which never
appears on any views where it is set (and Deadline is included on my timeline
through MS Project 2007).

Is this a known bug?

Jane
 
M

Marc Soester [MVP]

Hi Jane,

I use the Deadline in Project 07 and it works ok for me. I asume you are
refering to MS Project and not PWA's Project Center.
Is this correct?
 
J

Jane

Deadlines work fine in Project 2007.

I am referring to referring to Project Server 2007's Gantt Chart Formats and
the views displayed in PWA Project Centre

Jane
 