Thank you Jan! You are right, this basically show me the information in the Resource Usage view
I am relatively new to Project, but I have used VBA in Access before. Can I write a script of some sort to use a for loop to loop through the "Filtered by Resource" View for all Resources? If possible, where would I put this script so I can use it in Project
----- Jan De Messemaeker wrote: ----
Hi
It depends what exactly you are looking for
First, beware that some tasks may have more than one assignment - they wil
be sorted separately from the ones having just one of the resources
Secondly, be awore that summary tasks (which normally do not have resoruce
assigned to them) will be sorted in front of all other tasks - best is to g
to Tools, options, view, cross out "Show Summary Tasks
If you still want to go ahead
Projec
Sor
Sort by.
Fill out Resource Names, and Start in the second selection bo
CROSS OUT KEEP OUTLINE STRUCTUR
O
Apart from showing the tasks graphically, this view does not give mor
information than the Resource Usage view sorted by Start
HT
-
Jan De Messemaeke
Microsoft Project Most Valuable Professiona
http://users.online.be/prom-ade/index.ht
32-495-300 62
Deluth said:
I would like to know how I can view a Gantt chart of all my resources.
am able to view individual resource if I use the "filtered by resource", bu
this takes too long when I have to look at every resource in my project
Would someone show me how I can display the Gantt chart of all my individua
Resources (at once) sorted by Resource then Start