I'm using Visio 2007.
I'm working on a Gantt chart that spans multiple days, using hours as the
duration. When I have 1 task that is over the span of 2 days, the next
linked task always begins at the time that I previously designated to be the
start of the work day,instead of just starting off at the time the previous
task left off. So it looks like that the program is defaulting to the start
of the work day whenever you start off with a new day. Any ideas on how to
start the next task immediately after the last task?
I'm working on a Gantt chart that spans multiple days, using hours as the
duration. When I have 1 task that is over the span of 2 days, the next
linked task always begins at the time that I previously designated to be the
start of the work day,instead of just starting off at the time the previous
task left off. So it looks like that the program is defaulting to the start
of the work day whenever you start off with a new day. Any ideas on how to
start the next task immediately after the last task?