Gantt chart start/finish dates and actual start/finish dates.

C

Cynthia

I am new to Visio, having used Microsoft Project previously. I am trying to
show the "baseline" start and finish dates and the "actual" start and finish
dates of the same task. In project, this is possible and you get two bars on
the same task line. I can get the start and finish dates bar to communicate,
but when I insert new columns with actual start and finish dates, I don't get
another bar below the first bar in the same task. Is this possible in
Visio?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top