I spoke since to MS & found a 'workaround' from as there is no option to
change defaults (apparently this was 'bought-in' as an American product):
Select range of cells to change. Use Format>Protection>Text to unprotect the
text & then manually edit the contents of the cells. Reset protection is
req.
I can make the column start on any day of the week.
I spoke since to MS & found a 'workaround' from as there is no option to
change defaults (apparently this was 'bought-in' as an American product):
Select range of cells to change. Use Format>Protection>Text to unprotect the
text & then manually edit the contents of the cells. Reset protection is
req.
The original problem is that when you create Gantt chart with Date Options
for Months (Major units) & Weeks (Minor Units), Visio will display the week
dates columns for the Sundays - e.g. 2nd, 9th, 16th, 23rd, 30th under the
July header. This is not altered by the timescale range being set to a
Monday date.
The workaround answers the need for the week's column dates to display
starting on the Monday.