The information I see in PWA My Tasks page, Tasks Gantt View is not actual.
The problem is that I do not see my last actual work confirmed.
 
H

Hans

After accepting the actual work, did you:
- open the project to apply the task updates?
- Published the project to make the updated project schedule (including the actual work) available in PWA?

If not, try it and the Tasks Gantt View should be up-to-date again.

I hope this helps,
Hans



Projectopolis



íÉÈÁÉÌ ëÌÉÛÅ×ÉÞ wrote: The information I see in PWA My Tasks page, Tasks Gantt View is not actual. The problem is that I do not see my last actual work confirmed.
 
M

Marc Soester [MVP]

You need to make sure that you re-publish your project after acceptance of
the task. Only than will you see the latest information
Hope this helps
 