Y
yann
Dear all,
After posting several messages through this forum,
For my particular purpose, i want to use Ms Project Server for both a
Workflow management and a planning monitoring.
I wanted for a user to be as simple as possible to update task progress and
precise forecast in case of delay with the field "End". Moreover, not having
a full dedicated planer or PM, i have tried to automize as much as possible
valdiation "automaticaly update taks" but there were the publish issue which
i solved.
The Last issue were related to the slippage between one project to the other
one as i have different project linked together.
THe only way i understood to see the consequences of a slippage of one
project to the other one is that the PM (which in my case is the owner of all
the project) open Microsoft Project Plan so then he "accepts" the
modification so then the user can see the changes on PWA.
I needed initialy to have a real time update but i guess the PM will not
open Microsoft Project Plan every minute.
In our case, we plan so the PM to open all the projects every 2 hours so
update will be seen by the users.
Anybody got a better solution for my specific case,
Thanks
After posting several messages through this forum,
For my particular purpose, i want to use Ms Project Server for both a
Workflow management and a planning monitoring.
I wanted for a user to be as simple as possible to update task progress and
precise forecast in case of delay with the field "End". Moreover, not having
a full dedicated planer or PM, i have tried to automize as much as possible
valdiation "automaticaly update taks" but there were the publish issue which
i solved.
The Last issue were related to the slippage between one project to the other
one as i have different project linked together.
THe only way i understood to see the consequences of a slippage of one
project to the other one is that the PM (which in my case is the owner of all
the project) open Microsoft Project Plan so then he "accepts" the
modification so then the user can see the changes on PWA.
I needed initialy to have a real time update but i guess the PM will not
open Microsoft Project Plan every minute.
In our case, we plan so the PM to open all the projects every 2 hours so
update will be seen by the users.
Anybody got a better solution for my specific case,
Thanks