B
Broodmdh
I am tracking the progress of a software development project, and I'm
having trouble making Project work as I would expect it to (which may
mean that my expectations are unrealistic). I have a predetermined
number of tasks and resources, but I also have surprise-tasks (bugs,
issues in other unrelated systems which demand my resources etc). The
lifecylcle for each task takes it through several people's hands, over a
long period of time.
For example, one specific page may pass between 4 people before
completion. They will all devote varying amounts of time to it, and
most will not address it immediately after it's assigned to them (a lag
of several days is not uncommon). How can you use project to track the
effort (and whoever the task is currently assigned to etc) without
playing havoc with timelines? i would also prefer to have tasks
'unassigned', because otherwise I end up juggling tasks from person to
person. Ideally, a task wouldn't be assigned to a resource until that
resource is actually working on it, but it would still be taken into
account for determining the overall projects timeline. Is that even
possible?
I'm relatively new to MS Project, and I'm learning as I go, so I'm sure
that there are better ways to accomplish what I'm doing. Any advice
would be appreciated.
having trouble making Project work as I would expect it to (which may
mean that my expectations are unrealistic). I have a predetermined
number of tasks and resources, but I also have surprise-tasks (bugs,
issues in other unrelated systems which demand my resources etc). The
lifecylcle for each task takes it through several people's hands, over a
long period of time.
For example, one specific page may pass between 4 people before
completion. They will all devote varying amounts of time to it, and
most will not address it immediately after it's assigned to them (a lag
of several days is not uncommon). How can you use project to track the
effort (and whoever the task is currently assigned to etc) without
playing havoc with timelines? i would also prefer to have tasks
'unassigned', because otherwise I end up juggling tasks from person to
person. Ideally, a task wouldn't be assigned to a resource until that
resource is actually working on it, but it would still be taken into
account for determining the overall projects timeline. Is that even
possible?
I'm relatively new to MS Project, and I'm learning as I go, so I'm sure
that there are better ways to accomplish what I'm doing. Any advice
would be appreciated.