C
chris
I have set a baseline for my project and have been tracking progress. I have had tasks that have slipped so there ar
new start and finish dates which have been adjusted by project. Project automatically makes the "actual start" and
"actual finish" equal to the start and finish dates. This is really confusing because it looks like tasks may be completing.
Is there a way to control this so the actual start and finish are empty or "NA" until I actually go in and update them.
I know project will assume the task has started if the start date has passed is there a way to control this or at least control the finish date to not be set until I enter the date
Thanks
new start and finish dates which have been adjusted by project. Project automatically makes the "actual start" and
"actual finish" equal to the start and finish dates. This is really confusing because it looks like tasks may be completing.
Is there a way to control this so the actual start and finish are empty or "NA" until I actually go in and update them.
I know project will assume the task has started if the start date has passed is there a way to control this or at least control the finish date to not be set until I enter the date
Thanks