R
Roman Benko
I am new to Project and noticed that when I downloaded some of the sample
templates from here, the last task of every major section had a task titled
"section completed" with a duration of zero days. For example, if a major
section is titled "Analysis and Design", the last task of that section is
titled "Analyis and Design Completed" and has a duration of zero days.
Can someone explain the purpose of this? Isn't a section considered
complete if all of the tasks in it are marked as 100% complete? I am tempted
to omit this task, but am worried that it will come back to haunt me later.
Thanks in advance for your help.
templates from here, the last task of every major section had a task titled
"section completed" with a duration of zero days. For example, if a major
section is titled "Analysis and Design", the last task of that section is
titled "Analyis and Design Completed" and has a duration of zero days.
Can someone explain the purpose of this? Isn't a section considered
complete if all of the tasks in it are marked as 100% complete? I am tempted
to omit this task, but am worried that it will come back to haunt me later.
Thanks in advance for your help.