R
Rob
I have MSP 2007 Pro - Not using server yet though.
I built a scheduling using lets say "Analyst" at 150% availability
(representing two). 150% because we account for administrative time so the
most any reasource is avail is 75%. I now know the specific "Analyst"
resources.
How do I go about distributing the two resources accurately without pushing
the schedule to the right? I assume there is only(likely) one way to do so
in a complex schedule that will result in the same exact end date?
I built a scheduling using lets say "Analyst" at 150% availability
(representing two). 150% because we account for administrative time so the
most any reasource is avail is 75%. I now know the specific "Analyst"
resources.
How do I go about distributing the two resources accurately without pushing
the schedule to the right? I assume there is only(likely) one way to do so
in a complex schedule that will result in the same exact end date?