Hi Lesly,
View the Resource Usage view. Select the resource you wish to show the
information for. Show the Analysis toolbar and click the Analyze Timescaled
Data in Excel button.
In step 1 of the wizard, choose "Currently selected resources."
In Step 2 of the wizard, select Actual work, and remove Work as the field to
export.
In Step 3 select the date range and units.
In Step 4, choose to graph the data.
In Step 5, export the data.
Hope this is what you are searching for. Let us know how you get along.
Julie
 