I want to have a progress report that shows the following for a period of time:
Work; Baseline work; Remaining Work, Act Work and work
variance.
I want to be able to see at the summary level of the various tasks, the
amount of baseline work remaining at the end of the period. In other words,
the amount of baseline work within the period (ie 01/01/05 to 04/30/05) that
has not been accomplished at the end of 4/30/05.
I have tried two approaches:
1. Using the Task Usage View with Tracking and filtered by date.
Then I take the report and copy to excel. I then have to add up the hours by
individual tasks. I do this because the system reports all hours at the
summary task level. However I still end up with baseline hours that are
worked outside the requested period.
2. Run the same report above for the entire period, copy to excel
and then subtract the remaining baseline hours out of the summary totals.
So the question is can I produce the desired report within the system
without having to copy to excel and adjust.
If you have the time and would like to discuss over the phone my number is
(704) 357-5081.
Thanks for your time and effort.