M
MG Borrego
How can I generate a comprehensive project report that lists the tasks
assigned to each resource sorted by task start date? The "Who Does What"
report is very close to what we need except that the individual task
assingment table listed under each resource is by default ordered by task id
not start date. I was not able to figure out how to re-sort the assignment
schedule table.
I searched the online help and played with custom reports and table
definitions with no success. Is sorting this table by start date possible or
is there another way to generate this type of report? Help!
Thanks,
Marissa
assigned to each resource sorted by task start date? The "Who Does What"
report is very close to what we need except that the individual task
assingment table listed under each resource is by default ordered by task id
not start date. I was not able to figure out how to re-sort the assignment
schedule table.
I searched the online help and played with custom reports and table
definitions with no success. Is sorting this table by start date possible or
is there another way to generate this type of report? Help!
Thanks,
Marissa