Hi,
Since the installation of Project Web Access, I have been able to view
Resource Assignments for Generic Resources. However, since about last month,
no generic resources are writting assignment records to display.
For example, I can look at Task lists and see the generic resource assigned
to a particular task. But if I go into a Resource view and try to View
Resource Assignments I am not longer seeing any new records there.
Further to the mystery. The reason they are not showing is that no generic
resource assignment records are being written to MSP_Web_Assignments.
All this was working fine up until recently and to the best of my knowledge,
nothing has changed.
Any ideas out there folks?
Regards,
Brad
Since the installation of Project Web Access, I have been able to view
Resource Assignments for Generic Resources. However, since about last month,
no generic resources are writting assignment records to display.
For example, I can look at Task lists and see the generic resource assigned
to a particular task. But if I go into a Resource view and try to View
Resource Assignments I am not longer seeing any new records there.
Further to the mystery. The reason they are not showing is that no generic
resource assignment records are being written to MSP_Web_Assignments.
All this was working fine up until recently and to the best of my knowledge,
nothing has changed.
Any ideas out there folks?
Regards,
Brad