D
Darrell
If I want to report on the resource usage of select group across all
projects, I can use the Resource Availability in PWA and view the “Assignment
Work by Project†for that group. This shows me the aggregate work performed,
or to be performed, remaining availability and the capacity of the group for
the selected time period. However, what if some of my schedules still contain
generic resources for part of the time period I am interested in reporting on
i.e. through the remainder of this year.
Should I set all Generic Resource’s availability “Units†to “0%†so that
they do not add “capacity†to the organization and will still show work to be
performed? As long as I am not worried about the groups availability being
reduced is this a viable approach for showing the work performed or to be
performed?
projects, I can use the Resource Availability in PWA and view the “Assignment
Work by Project†for that group. This shows me the aggregate work performed,
or to be performed, remaining availability and the capacity of the group for
the selected time period. However, what if some of my schedules still contain
generic resources for part of the time period I am interested in reporting on
i.e. through the remainder of this year.
Should I set all Generic Resource’s availability “Units†to “0%†so that
they do not add “capacity†to the organization and will still show work to be
performed? As long as I am not worried about the groups availability being
reduced is this a viable approach for showing the work performed or to be
performed?