R
reza
Hi All,
Another question from me...
when setup project plan i use generic resource, then i import project plan
to project server using import wizard.
1. Should we import generic resources to project server? and if i don't
import generic resources to project server, what will happen? is it bad?
2. can generic resources see his/her task in project plan? how?
3. in my task there were feature "assign task to me". In what condition that
feature will use/enable?
a lot of thanks for your explanation.
reza
Another question from me...
when setup project plan i use generic resource, then i import project plan
to project server using import wizard.
1. Should we import generic resources to project server? and if i don't
import generic resources to project server, what will happen? is it bad?
2. can generic resources see his/her task in project plan? how?
3. in my task there were feature "assign task to me". In what condition that
feature will use/enable?
a lot of thanks for your explanation.
reza