Generic Resources

B

Bill M.

This doesn'e seem to have been published. Sorry for the duplicate if
it appears sometime today.

I would like to know how people are handling generic or contract
resources in project enterprise. Specifically, suppose I hire a web
developer for $5000, assign a task to them in the project. A week
later I need another web developer but the fee is $8000 and so on. The
cost tables would allow be 5 different cost (A-E). What happens after
the table are full? It doesn't make sense to try to use effectivity
dates as some could overlap others.

Any suggestion as to how to handle this in an enterprise environment?
 
B

Bill M.

Thanks for the suggestion Jim. I believe this will wor fine for me.
I'll be able to keep the variable cost resources, both work and
material, as enterprise and still allow costs specific to each
resource to be reflected in its respective project.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top